Contact the Community Development Department if you have additional questions about a development project.

This page will be continuously updated as new information becomes available.  Page last updated 3/20/24.

If you are unable to attend any of the public meetings or public hearings, or if you would like to leave a public comment for any of the information above, please select the “Leave a Public Comment” button.  Your comments will be made part of the public record. Please note: Any comments left without verifiable contact information will be disregarded.

Leave a Public Comment
FAQS
147 & 151 Gettysburg Pike (7-Eleven Site)
  • Address: 147 & 151 Gettysburg Pike
  • Project Description: Consolidation of two parcels, demolition of an existing building, and construction of a 5,000 sq. ft. convenience store with gas pumps (7-Eleven) at 147 Gettysburg Pike, and a 3,000 sq.ft. restaurant with drive-through at 151 Gettysburg Pike (TBD)
  • Submission Date: June 06, 2020
  • UAT File # 20-06-01
  • Site Plan: Site Plan Recorded 05/18/22
  • Other Documents: 7-Eleven Isometric Building Elevation
  • Planning Commission: Recommended approval on 07/207/20
  • Board of Commissioners: Conditionally approved on 10/07/20
  • Project Status: Currently under construction
2210 Aspen Drive (JoJo's Pizza)
2401 Arcona Road
  • Address: 2401 Arcona Road
  • Project Description: Subdivide existing tract into three lots
  • Submission Date: December 1, 2023
  • UAT File # 23-12-01
  • Site Plan: Site Plan-Draft 12/01/23Site Plan-Draft 01/05/24 (Revised)
  • Planning Commission: Reviewed on 12/18/23 and action tabled for further review.  Recommended conditional approval on 01/29/24
  • Board of Commissioners: Review tabled on 03/06/24.  Future review date TBD.
  • Project Status: Currently under review.  
2509 Mill Rd
2520 Mill Rd
  • Address: 2520 Mill Rd
  • Project Description: Construction of six townhomes
  • Submission Date: April 29, 2021
  • UAT File # 21-04-29
  • Site Plan: Site Plan Recorded 07/20/22
  • Other Documents: Townhome sketch
  • Planning Commission: Recommended approval on 05/24/21
  • Board of Commissioners: Conditionally approved on 07/21/21
  • Project Status: Complete.
900-908 Gettysburg Pike
  • Address: 900-908 Gettysburg Pike
  • Project Description: Subdivide the existing two lots into three lots to separate the existing buildings.
  • Submission Date: 10/25/23
  • UAT File # 23-10-25
  • Site Plan: Site Plan-Draft 10/25/23Site Plan-Draft 01/03/24 (Revised); and Site Plan-Draft 02/28/24 (Revised)
  • Zoning Hearing Board:  Case # 23-09.  A public hearing was held on 12/14/23 and a variance was granted to permit one lot of 8,819 square feet instead of the minimum 10,000 square feet of area for the subdivision of property.
  • Planning Commission: Recommended conditional approval on 01/29/24.
  • Next review date: Pending review by the Board of Commissioners on 03/20/24.
  • Board of Commissioners: Conditional approval given on 03/20/24.
  • Project Status: Pending completion.
Andreozzi, Benjamin & Ciara
  • Address:  514 Jonagold Circle & 601 Autumn Court
  • Project Description: Lot consolidation of two lots into one lot.  
  • Submission Date: November 30, 2023
  • UAT File #23-11-30
  • Site Plan: Andreozzi Site Plan 11/30/23 Draft
  • Planning Commission: Conditionally approved on 12/18/23
  • Project Status: pending completion
Arborview
  • Address:  418 Gettysburg Pike 
  • Project Description: Development of 26 single-family detached dwellings
  • Submission Date: March 1, 2018
  • UAT File # 18-03-01
  • Site Plan: Site Plan Recorded 10/15/19
  • Other Documents: Traffic Impact Study Draft 04/09/18
  • Planning Commission: Recommended approval on 04/30/18
  • Board of Commissioners: Conditionally approved on 06/06/18
  • Project Status: Currently under construction
Autumn Chase PRD

Autumn Chase PRD was tentatively approved in May 2012 for the construction of 295 homes.  The development will consist of a mix of single-family detached dwellings, townhomes and duplexes over eight phases.

Autumn Chase PRD Master Plan

Autumn Chase PRD - Rezoning Request

  • Project Description: Rezone a portion of land within the Autumn Chase development from Low-Density Residential (R-1) to Medium-Density Residential (R-2) and apply the Planned Residential Development (PRD) Overlay to the rezoned land area.  This would allow for the entire Autumn Chase development, if approved, to be within the PRD Overlay District.  The portion of land proposed to be rezoned would be 14.8 acres.  Applicant would also develop the land with an additional 22 single-family detached homes within the Autumn Chase development.
  • Petition Request:  Petition Request and Maps
  • Board of Commissioners: Considered petition on 03/20/24.  Authorized it to move forward for review by the Planning Commission and Cumberland County Planning Commission. 
  • Planning Commission: Scheduled for review on 04/29/24.
  • Board of Commissioners: TBD
  • Public Hearing: TBD
  • Project status:  Under review

Autumn Chase, Phase 1 

  • Address: Hertzler Road
  • Project Description: Construction of 39 single-family detached dwellings
  • Submission Date: December 12, 2018
  • UAT File # 15-12-18
  • Site Plan: Site Plan Recorded 10/06/21
  • Planning Commission: Recommended approval on 08/28/17.  Re-approved on 07/27/20
  • Board of Commissioners: Conditionally approved on 10/04/17.  Re-approved on 09/02/20 and again on 09/15/21
  • Project Status: Complete

Autumn Chase, Phase 2

  • Address: Hertzler Road
  • Project Description: Construction of 32 townhomes and 24 duplex units.
  • Submission Date: July 1, 2022
  • UAT File # 22-07-01
  • Site Plan: Site Plan Recorded 07/27/23
  • Planning Commission: Reviewed on 08/29/22.  Recommended conditional approval.
  • Board of Commissioners: Conditionally approved on 09/07/22.  Recorded 07/27/23.
  • Project Status: Currently under development

Autumn Chase, Phase 3 

  • Address: Hertzler Rd
  • Project Description: Construction of 39 single-family detached dwellings
  • Submission Date: November 1, 2021
  • UAT File # 21-11-01
  • Site Plan: Site Plan Recorded 09/22/22
  • Planning Commission: Recommended approval on 12/27/21
  • Board of Commissioners: Conditionally approved on 01/03/22
  • Project Status: Currently under development

Autumn Chase, Phase 4 

  • Address: Hertzler Rd
  • Project Description: Construction of 28 townhomes.
  • Submission Date: May 1, 2023
  • UAT File # 23-05-01
  • Site Plan: Phase IV Site Plan Draft 05/01/23Draft Site Plan Revised 08/10/23
  • Planning Commission: Conditionally approved on 05/22/23
  • Board of Commissioners: Conditionally approved on 09/06/23
  • Project Status: 

Autumn Chase, Phase 5 

  • Address: Hertzler Rd
  • Project Description: Construction of 35 single-family detached dwellings
  • Submission Date: January 31, 2023
  • UAT File # 23-01-31
  • Site Plan:  Site Plan Recorded 02/12/24
  • Planning Commission: Recommended conditional approval on 02/27/23
  • Board of Commissioners: Conditionally approved on 04/05/23.
  • Project Status: Currently under development
Banzhoff
  • Address: 1031 Gettysburg Pike.  Development access off of Grantham Road and Gettysburg Pike
  • Project Description: Preliminary plan for the construction of 54 townhomes and 9 single-family detached dwellings over three phases.
  • Submission Date: December 12, 2012
  • UAT File # 12-12-03B
  • Site Plan: Preliminary Site Plan 2021-0727
  • Other Documents: Traffic Impact Study 11/2013
  • Planning Commission: Recommended approval on 06/30/14
  • Board of Commissioners: Conditionally approved on 05/06/15.  A revised phasing plan was approved on 08/18/21
  • Legal Status:  Applicant filed an appeal to the Court of Common Pleas on 06/04/15.  The court opinion was issued on 01/21/16.  Applicant filed an appeal to the PA Commonwealth Court on 02/22/16.  Mediation ensued and a joint motion to approve a revised plan was agreed upon on 01/12/22.  The appeal was dismissed on 01/18/22
  • Project Status: Preliminary Plan Review complete.  Applicant may submit final subdivision and land development phased plans for approval.

Subdivision of Lots 2A, 5C, and 6D

  • Project Description: Subdivision of Lots 2A, 5C, and 6D, which are located west of US Route 15 (along Gettysburg Pike).  No structures or land development are proposed with this subdivision plan. 
  • Submission Date: October 2, 2023
  • UAT File # 23-10-02
  • Site Plan:  Banzhoff Draft Plan 10/02/23Banzhoff Site Plan-Draft 11/17/23 (Revised)Banzhoff Site Plan-Draft 01/03/24 (Revised)
  • Planning Commission: Reviewed on 11/27/23.  Action tabled.  Review continued on 12/18/23.  Conditional approval was recommended.
  • Board of Commissioners:  Conditionally approved on 01/17/24
  • Project Status:  
Bridge 247 Replacement - York County
Project: York County Bridge 247 Replacement

Address:  Bridge No. 247 over Yellow Breeches Creek in Monaghan Township, York County and in Upper Allen Township, Cumberland County. The bridge is located on North Grantham Road and Mill Road.

Project Description: At the May 5, 2022 Board of Commissioners' meeting, a representative of Herbert, Rowland & Grubic, Inc. (HRG) shared plans to replace York County Bridge 247.  Here are the exhibits: Bridge Improvement Plan Exhibits  

The project is a combined effort of York and Cumberland Counties.  York County is taking the lead on the project and serves as the local project sponsor. For more information, visit York County's Bridge Program site at https://yorkcountypa.gov/340/Ongoing-Construction.

Project Status: Permitting Phase

Anticipated Construction: Spring - Fall 2025

Questions or concerns related to the project may be addressed to HRG's project engineer, Matthew J. Lena, P.E., at mlena@hrg-inc.com.
Georgetown, Lot 36A
  • Address: E Elmwood Ave, Lot 36A
  • Project Description: Reclassify a lot from a retention basin to a proposed single-family building lot
  • Submission Date: February 1, 2024
  • UAT File # 24-02-01
  • Site Plan: Lot 36A Site Plan-Draft 02/01/24; Lot 36A Site Plan-Revised Draft 04/08/24
  • Other Documents:
  • Planning Commission: Reviewed on 02/26/24 and action tabled.  Scheduled for continued discussion on 04/29/24.
  • Board of Commissioners: 
  • Project Status: Under review
Gettysburg Pike, Lot 4
  • Address: 1819 Gettysburg Pike
  • Project Description: Construction of two commercial office buildings
  • Submission Date: Preliminary Plan submitted 12/03/18.  Final Plan submitted 09/30/19
  • UAT File # 19-09-30
  • Site Plan: Site Plan Recorded 05/15/20
  • Other Documents: Traffic Impact Study 12/17/18
  • Planning Commission: Recommended approval on 10/28/19
  • Board of Commissioners: Conditionally approved on 11/20/19
  • Project Status: 1st building (currently Penn State Health Medical Group) is complete.  2nd building pending construction
Historic District Reassessment
The Township will begin working on an update to Chapter 155 .  The information regarding this amendment has been moved to here: Ordinance Amendments

Update: 12/22/22
K-Care (Genius Kids) Daycare

K Care (Genius Kids) Daycare

Legacy Park-Allendale Realignment

Legacy Park is a new home community located within Mechanicsburg Borough.  The development consists of various townhomes, single-family dwellings, multi-family apartments, and a commercial area.  As part of Phase 4, site improvements to a portion of Allendale Road within the township and lot add-ons are proposed for abutting property owners within the Township.

For additional information regarding Legacy Park and its various phases of development, contact Mechanicsburg Borough.

Legacy Park, Phase 4 - Allendale Realignment

Meadowview
Meadowview Estates, Phase VI.

Construction of 36 single-family detached dwellings over three phases.  Phases VI-A and VI-B are complete.

Meadowview Estates Phase VI Development Plan

Meadowview Estates, Phase VI-C

  • Address: Southview Drive and North Meadow Circle
  • Project Description: Construction of 14 single-family detached dwellings
  • Submission Date: February 1, 2017
  • UAT File # 17-02-01
  • Site Plan: Phase VI-C Site Plan Recorded 06/07/17
  • Planning Commission: Recommended approval on 02/27/17
  • Board of Commissioners: Conditionally approved on 03/15/17
  • Project Status: Currently under development
Mills at Shepherdstown Crossing

The Mills at Shepherdstown Crossing

  • Address: 211-237 Gettysburg Pike
  • Project Description: Consolidation of several lots, and construction of multiple buildings to create a mixed-use development with a total of 54 apartment (multi-family) dwellings (in Buildings #1 and #2) and 44,000 sq. ft. of commercial space.  Building #3 proposed as a 3-story mixed-use building for future office/retail/and restaurant space.  Building #4 proposed as a potential restaurant space with a drive-through facility.  Building #5  proposed as a Burger King restaurant with a drive-through facility.
  • Submission Date: April 1, 2021
  • UAT File # 21-04-01
  • Site Plan: Site Plan Recorded 01/25/22
  • Traffic Studies: Traffic Impact Study Draft 01/25/22Appendix A-Part 1Appendix A-Part 2Appendix A-Part 3
  • Other Documents:   Burger King Sample DesignApartment Building Sample Design
  • Planning Commission: Recommended approval on 05/24/21
  • Board of Commissioners: Conditionally approved on 07/21/21
  • Project Status: Currently under construction.

Chick-fil-A at The Mills at Shepherdstown

ModWash
  • Address: 127 Kim Acres Drive
  • Project Description: Construction of a 4,464 sq. ft. automate conveyor style car wash with vacuum facilities (ModWash)
  • Submission Date: November 29, 2021
  • UAT File # 21-11-29
  • Site Plan: Modwash Draft Plan 02/08/22Site Plan 07/26/23-Recorded Version  Amended plan below.
  • Other Documents:
  • Planning Commission: Recommended approval on 01/31/22
  • Board of Commissioners: Conditionally approved on 03/16/22.  Request for re-approval heard on 10/19/22 and tabled until a new traffic study was completed.  The new traffic study has been completed.  Conditionally approved on 03/15/23
  • Project Status: Plan recorded 08/22/23

Revised Plan for ModWash

  • Project Modification Update:  Alter the drive aisle width between the two vacuum parking areas from 24 feet to 28.8 feet (with a taper to 27.3 feet), increase one side of  the vacuum parking spaces from 19 feet in length to 20 feet, decrease the stacking lanes from 33 feet to 31.5 feet and decrease the curb area between the stacking lanes and the vacuum area from 4 feet to 1.5 feet.  The sidewalk width and distance between the vacuum area and the car wash conveyor building will decrease by one foot.  The revised plan also includes a 6 foot high, 58 foot long white vinyl privacy fence and 8 arborvitae trees.  Seven (7) foot high Hardie board enclosures will also be installed around the vacuum producers.
  • Site Plan: Revised Plan-Draft 10/31/23 and Trash Enclosure Design & FenceModwash Revised Recorded Plan 01/09/24
  • Board of Commissioners:  Reviewed  on 11/15/23 and conditionally approved.  Fence line and row of arborvitae trees were extended.  Revised plan recorded 01/09/24.
  • Project Status:  Currently under construction
Oakwood Hills
Oakwood Hills 

Preliminary Plan submitted May 01, 2017 for Phase 1

Oakwood Hills Phase 1A

Submitted September 9, 2017  for Phase 1A

UAT File # 17-09-01B.  Project Complete.

Oakwood Hills Phase 1B

Submitted April 1, 2019 for Phase 1B

UAT File # 19-04-01.  Project Complete.

Oakwood Hills Phase 1C

Final plan not yet submitted.
Pennington
  • Address: Mt. Allen Drive and Pennington Drive
  • Project Description: Consolidation of the existing farm house and open space land, and construction of 38 single-family detached dwellings and several private open space lots.
  • Submission Date: December 3, 2007
  • UAT File # 07-12-3A and 07-12-3B
  • Site Plan: Site Plan Recorded 08/18/08
  • Planning Commission: Recommended approval on 12/17/07
  • Board of Commissioners: Conditionally approved on 06/18/08
  • Project Status: Currently under development
Tattersall
  • Address: West Winding Hill Road and South York Street
  • Project Description: Subdivision of 66 acres from the Gate of Heaven cemetery. Construction of 71 single-family detached dwellings in Phase 1.
  • Submission Date: October 1, 2019
  • UAT File # 19-10-01
  • Site Plan: Site Plan Recorded 03/16/21
  • Other Documents: Transportation Impact Study 02/28/20
  • Planning Commission: Reviewed on 12/30/19, 04/27/20, and 06/2920. Recommended disapproval on 06/29/20
  • Board of Commissioners: Conditionally approved on 09/16/20
  • Project Status: Currently under construction
Terraces at Shepherdstown
  • Address: Gettysburg Pike and Terrace View Lane
  • Project Description: Construction of 37 townhomes
  • Submission Date: February 1, 2011
  • UAT File # 11-2-1C
  • Site Plan: Site Plan Recorded 02/04/21
  • Planning Commission: Recommended approval on 02/28/11
  • Board of Commissioners: Conditionally approved on 06/15/11
  • Project Status: Currently under construction
Willows at Ashcombe Mansion
Transfer of a Liquor License

A public hearing was held on November 16, 2022 at 6:30 P.M.  Following the close of the public hearing, the Board of Commissioners adopted Resolution # 1073 approving the intermunicipal transfer request of a restaurant liquor license from Fox Foods, Inc., d/b/a/ CJs American Pub & Grill in Shippensburg Township, Cumberland County to the Willows at Ashcombe Mansion in Upper Allen Township, Cumberland County, PA.

Tavern 1891

Winding Hills PRD

Winding Hills PRD

 Winding Hills PRD Development Phasing Plan

  • Stages 1, 2, 3, 4, 5 (5A-Braeburn Estates portion only), 6, and 7 (Sections I and II) are complete.

Winding Hills, Stage 5(B), Lots 325-360:

  • Address: McIntosh Drive and Apple Hollow Road
  • Project Description: Construction of 36 single-family detached dwellings
  • Submission Date: March 1, 2017
  • UAT File # 17-03-01B
  • Site Plan: Site Plan-Draft 03/24/17
  • Planning Commission: Recommended approval on 03/27/17
  • Board of Commissioners: Conditionally approved on 05/03/17
  • Project Status: Currently under construction

Winding Hills, Stage 5(C), Lots 361-395:

  • Address: Waltana Court and Apple Hollow Road
  • Project Description: Construction of 35 single-family detached dwellings
  • Submission Date: May 1, 2018
  • UAT File # 18-05-01C
  • Site Plan: Site Plan -Recorded 10/14/20
  • Planning Commission: Recommended approval on 05/21/18
  • Board of Commissioners: Conditionally approved on 06/06/18
  • Project Status: Currently under construction

Winding Hills, Stage 8(A), Lots 420-438, 465-471, J&K:

  • Address: Hill Side Drive, Macoun Drive, and Spring Wood Lane
  • Project Description: Construction of 26 single-family detached dwellings and 24 townhomes
  • Submission Date: June 1, 2017
  • UAT File # 17-06-01B
  • Site Plan: Site Plan-Recorded 06/01/20
  • Planning Commission: Recommended approval on 06/26/17
  • Board of Commissioners: Conditionally approved on 05/15/19
  • Project Status: Currently under construction

Winding Hills, Stage 8(B), Lots 439-464, Lot L: 

  • Address:
  • Project Description: Construction of 26 single-family detached dwellings and 41 townhomes, and creation of Lot L for future clubhouse use.
  • Submission Date: December 1, 2020
  • UAT File # 20-12-01
  • Site Plan: Site Plan-Recorded 07/22/21
  • Planning Commission: Recommended approval on 12/21/20
  • Board of Commissioners: Conditionally approved on 01/20/21
  • Project Status: Currently under construction

Winding Hills, Stage 8, Lot L:

  • Address: Macoun Drive and Aurora Drive
  • Project Description: Construction of a 2,740 sq. ft. clubhouse area for residents in Stage 8.
  • Submission Date: January 1, 2022
  • UAT File # 22-01-03
  • Site Plan: Clubhouse Site Plan Recorded 07/19/22
  • Other Documents: Clubhouse Design Draft
  • Planning Commission: Recommended approval on 01/31/22
  • Board of Commissioners: Conditionally approved on 03/16/22
  • Project Status: Currently under construction